Connect with us

Sustainable Development

The Decade of Mega Hydropower Projects

Avatar photo

Published

on

These mega hydropower projects planned to be completed in the next 10 years will transform the power sector, agriculture, and manufacturing sector of the country. Socioeconomic development will also be ushered with these projects. There is a need to support these mega projects at all levels.

Pakistan has been blessed with enormous natural resources ranging from mountain peaks, world largest glaciers masses after polar region, diverse climates, mountainous regions, plains and deserts. One of these bounties of Almighty Allah are the frozen waters of the north-called glaciers. These frozen waters provide source of water to more than 60% of the population in three provinces of the country. This water is also source of one of the world largest irrigation systems also called Indus River System (IRS). Nature has blessed these waters with vast opportunities of hydropower generation but unfortunately, the successive Government have not been able to produce sufficient energy from water. As a result, we are heavily dependent on thermal power plants run by coal and fossil fuels. This energy is both expensive and detrimental for environment. According to some estimates, the Indus Water in the north has a capacity to generate about 100,000 Mega Watts of electricity, but today only 10,000 MW is produced which is only 10% of the capacity of power generation. The increasing prices of fossil fuels have also led to mammoth increase in the power prices. 

The present Government must be credited to initiate mega power projects in the country after 30 years. In one decade (2018-2028), the ten mega hydropower generation projects will be completed and the decade has been named as “Decade of Dams”. The storage capacity in Pakistan will increase from 13.6 Million Acre Feet (MAF) to 25.3 MAF. This will additional irrigate about 3.5 Million acres of new land, which will usher Agri-revolution in the country. In next 4 years, the hydel power capacity of the country will increase by 4500 MW and by 2029, it will further add 9000 MW, hence in next 8 years, the hydel power capacity of the country will be doubled. With the completion of these mega projects, 35000 new jobs will be created, which will improve the socio-economic conditions of the country. To ensure urban water security, 950 Million gallons of additional water will be provided daily. These mega projects include Dimar-Bhasha Dam, Dassu Hydropower project, Mohmand Dam, Kurram Tangi Dam, Nai Gaj Dam, Extension of Tarbela Dam, Harop Hydropower Project, Reconstruction of Sindh Barrage, Extension of Kachi Canals and Karachi Greater Water Supply Scheme. Further details of these dams are given as follows: 

  1. Diamer-Bhasha Dam (DBD):  It is one of the largest Concrete Roller Compacted dam, which is under construction at 40 km from Chilas city. The designed storage capacity of the dam is 8 MAF. On completion, DBD will produce 4800 MW of electricity. Due to construction of new dam at the upstream end, the silt load of the water stored in Tarbela Dam will substantially reduce and its working life will be increase by 36 years. The height of the dam is 272 meters and it is comprised of 8 spillways. Currently the project is being constructed by China Power and FWO. The commissioning of the project will require at least 10 years and extensive investment as well as foreign exchange. 
  2. Dassu Hydrpower Project (DHP): This project is being constructed on the run of river at 7 km from Dassu to Chilas, which is at 345 km from Islamabad. The project will produce 4320 MW on completion. In first phase six units will be completed to generate 2160 MW whereas in second phase, its capacity will be doubled. The estimated completion cost of the project is Pak Rupees 510 Billion which also includes 218 Billion of foreign exchange. During construction of the project, 37 km of the road will be shifted towards the right side of the river. The project requires about 10,000 acres of land. Half of the land has been already acquired and the acquisition of the remaining land is in process. The project is expected to be completed by 2026. 
  3. Mohmand Dam: This was previously called as Munda Dam, which is being constructed over the River Swat at 37 km from Peshawar towards North. On completion, the project will generate 740 MW of power and irrigate 15000 acre of land. The return of the dam will include 5 billion from water storage, 120 billion of power generation and 80 Million from flood mitigation every year. The dam is constructed from stone and concrete and its completion will usher as era of prosperity in the region. 
  4. Harpo Power Project: This project is located on the left bank of River Indus, at 75 km towards north of the Skardu city of Baltistan. On completion, the project will produce 34 MW power and will be completed with an estimated cost of Rs. 9 billion including 6 billion foreign exchange.       
  5. Extension of Tarbela Dam: The 5th extension project of Tarbela Dam has been started in August 2021 and it is expected that the project will be completed in next 4 years at total cost of PKR 82 billion. With the completion of this project, an additional 1410 MW of power will be generated. Besides hydropower generation, the project will create recreational facilities, developing fishing and excursions etc. 
  6. Kurram Tangi Dam: This multi-purpose project is being constructed on the kaito River, which become Kurram river at the downstream in North Waziristan, about 14 km upstream of Kurram Garhi Headworks and 32 km north of Bannu City. Besides generating 83 MW of power, the project will also irrigate 16,000 acres of land. This will improve garniture in the region. 
  7. Nai Gaj Dam Sindh: This dam is currently under construction in the Kirthar  range at Gaj River at about 65km North West of Dadu City. The height of the dam is about 194 km, which will produce 4.2 MW and store 300,000 Acre feet of water. The estimated cost of the project is 16 billion and will be completed in next 2 years. It will irrigate about 28,000 acres of barren land. Nai Gaj Dam will supply 50 cusecs of water to the Lake Manchar for decreasing its pollution. Furthermore, the water will also be supplied from the dam to Kachho desert and area of Kohistan in Dadu District. 
  8. Improvement of Sindh Barrage: Under this project, the performance, safety and efficiency of the Sukkar and Guddu barrages will be improved. This will be improving the irrigation system of the province. This project is being constructed with the loan from World Bank at a cost of US$ 140 Million. 
  9. Extension of Kachi Canals: This project will be completed at PKR 20 billion during current year. The existing Canal irrigation system will be extended by 40km, which will provide irrigation water to 30,000 acres of barren land in Dera Bugti. The project has high significance for eradicating poverty in the region. Thousand acres of barren land in Dera Bugti and Sui areas will be irrigated from this water. 
  10. Karachi Greater Water Supply Scheme: The project remained suspended for two decades, but the present Government has reviewed its design and has planned to complete it by end of 2023. This project will provide about 260 Million Gallons of water per day to Karachi.  The project is jointly sponsored by Federal and Provincial Government and is included in the Prime Minister Package for Karachi.

About Author

Opinion

Development Planning in Gilgit-Baltistan – The Missing Link  {A reflection}

Avatar photo

Published

on

Mr. Sajjad Hyder, Chief Economist, Planning & Development department has recently retired from his service after serving almost three decades, commencing from April 1993 to November 30, 2022. He, as Chief Economist, was responsible for leading public Investment management policies for designing and implementing various socioeconomic development projects and programs in the region.  Moreover, concoction of substantive policies for socioeconomic development in all sections was also part of his job responsibilities.

The retired officer, Mr. Sajjad Hyder, has shared the following reflection, regarding public investment management in GB, which is based on his 30 years of exposure as a development planning practitioner:  

Development Planning in Gilgit-Baltistan – Missing Link

Historical background: The development economics was born immediately after the second world war with the birth of the Breton Woods international financial system to facilitate development and eradicate poverty in the countries that were emerging out of colonialism. The Planning commission Pakistan was formally established in 1953 with the Harvard Advisory Group (HAG) officially became its coach soon after. Based on their methodology, the country introduced formal 5-year planning in 1955 which with periodic interregnums continues until today. In Gilgit-Baltistan, development planning starts with the inception of 2nd Five Year plan by establishing a Planning Cell in 1971.

It is not out of place here to say that most of the project cycle management components in GB have fallen into misuse, while others have developed serious defects. Following are the major gaps, in my observation over last 30 years with the department:

REASONS OF INEFFICIENCY IN DEVELOPMENT PLANNING IN GILGIT-BALTISTAN:

As indicated earlier, Public Investment Management in Gilgit Baltistan starts from 2nd five-year plan.  This system served well the needs of this region in
early stages as the planning & development department was an empowered organization headed by a development commissioner in BS 20. Over time, however, the system developed several problems due to degradation of the organization in view of successive political developments in the region. Presently, Gilgit-Baltistan’s PIM system (development planning) is mere shadow of the concept given by the Harvard Advisory Group, meaning, in capacity, influence and effectiveness.

To understand the sources of inefficiency, it is necessary to review all the stages in the public investment process to identifying gaps and weak points in the processes and procedures.

 Guidance and Screening: Identification and screening components of PIM are badly compromised due to atrophy of economic planning in Gilgit-Baltistan.  Three broad factors were mainly responsible for the waning performance of the PIM system in GB: 

1) Rigidities of the PIM system: The structure of the economy changed from a public sector led to a private sector led economy. This structural changed called for a different role of the planning system, in general, and particularly, the role of P&DD. This required different skills and competencies than what are available with the department. 2) Dominance of crisis management over economic management: As projects started to slow down due to economic policy and planning adopted in firefighting mode. Longer term planning as well as public investment became casualties of the crisis mode which has preoccupied the GB Government for the last several years.

3) A sharp decline in the capacity of the PIM system in GB: With no medium-term plan or strategy available to define the sectoral and sub-sectoral priorities of the government, the project identification process became largely ad-hoc, with identified projects reflecting more the priorities of political leadership than those established through a well thought out plan. The void left by abandonment of the planning process is largely filled by the politicians, where a large number of projects are identified by politicians, or by the line-departments on directives of the politicians.
Ironically, the Planning Commission manual, provides ample guidance for identification, appraisal, and implementation of various programs / projects but of no use in GB.

Project Preparation and Appraisal: In the beginning, the quality of project preparation and appraisal was quite satisfactory. However, over time, these functions weakened, mainly due to following reasons:

  • With mounting fiscal difficulties, the line departments faced an increasing
    squeeze on their operational (recurrent) budget. Inclusion of a project into
    the ADP therefore became a mode of getting additional fiscal resources
    for the line departments, from which it can finance some of operational
    needs left unmet by inadequate recurrent budget. There was therefore a
    big enough incentive for the line departments to get as many as possible
    projects into the ADP as soon as possible. This forced them to cut
    corners on project preparation and pull all strings and levers to get project
    approved.  {Roughly, only 3 percent of development expenditure goes to create or acquire physical assets, whereas 31 percent is spent on operation expenditure}.
  • Political intervention in the development process increased adversely
    affecting the quality of project preparation and the moral of
    development-related staff in the departments and P&DD. There never has been any tradition in GB of undertaking ex ante or ex-post independent reviews of the preparation and appraisal process even for important projects.
  • Games” in the project preparations and approval processes: Limited capacity of the P&DD to properly appraise projects has given rise to some “gaming” behavior within the line departments to get whatever they want from the project approving authorities by deliberately include unwanted expenditure items (e.g. a large number of vehicles) in the project design just to distract the P&DD’s appraisal team to focus on these items, leading to a less than required focus on other areas and costs of the project. {The end result is leading to implementation delays, changes in scope and design of the project, cost overruns and consequently loss in benefits from the projects}.
  • Project Selection and Budgeting: Once a project is included in ADP in principle, administrative and political wheels start moving to get the project approved, irrespective of whether funds for the project are available or not, and it is technically viable or otherwise.  This leads to a number of projects making into the ADP with insufficient (at time a “token” allocation). This allocation is usually not even enough to pay for the
    salaries of the project staff. Moreover, this also leads to thin spreading
    of resources across other projects. As such, many projects get under-financed, which causes implementation delays, and a large throw-forward. A large throw-forward leaves little room for the incoming new government to implement its development agenda with full vigor. This has created a number of implementation issues undermining the efficiency of public investment.

Project Implementation: Project Implementation has been a weak area in GB. For ADP projects, shortcomings in project identification, preparation, appraisal, and approval processes make implementation very difficult. In addition, projects are usually managed by staff taken form regular cadres of government, with limited project management skills.

At times project management is assigned as an “additional responsibility” along with the person’s normal work. Moreover, procedures governing project financing, procurement and contracting are overly cumbersome. Hence, implementation delays and the consequent cost escalations are a norm rather than an exception for ADP.

Public Procurements: Weak procurement practices remain one of the major reasons for inefficiencies in public expenditure, including public investments as procurement is a highly technical subject. In addition, the volume of public procurements is huge, both in size and number. There are not enough skilled procurement specialists within the GB Government to manage all these procurements. Moreover, weak accountability and defective bidding and contract documents have given rise to corrupt contracting procedures and practices which directly undermine the efficiency of public expenditure in general, and particularly public investment.

Monitoring & Evaluation: Despite being a function mandated to both the line departments and the P&DD, project monitoring requires considerable improvements. To date, most of monitoring that is undertaken relates to inputs and compliance with procedures and processes, output and impact monitoring continues to be considered as outside the purview and mandate.  

Project Completion and Service Delivery: Although procedures for completing a project and soliciting operational resources are well laid out, yet they are hardly ever followed. Project completion report (PC-IV) is filed only in cases where the project requires recurrent expenditure allocation to be operational. Following are the reasons for inadequate allocation of operational budget to a newly completed project:

i) Weak estimates of operational resources: While preparing the PC-I, the line
departments deliberately understate the recurrent expenditure implications of
the project. This is done to improve the chances of getting the project
approved and included in the development budget. The finance authority
takes these estimates very seriously when making operational allocation after
completion of the project.

ii)  Implementation delays not only lead to escalation in project cost, but also in recurrent expenditure required to make the project operational.

iii)  Inadequacy of R&M allocations lead to deterioration in quality of service
delivered by the projects, reducing value for money under projects.

Missing Links in Functioning of Planning & Development Department: P&DD GB has thus become a project approval body where most of the projects are not identified based on technical considerations or as part of a shared approach to maximizing growth and welfare. These developments adversely impacted the value for money under development.
At all stages of the project, P&DD is supposed to keep track of performance. However, this tracking is now not happening to maximize project performance. At the project initiation, the PC1 form requires a full cost-benefit and economic analysis of the project to be presented to the approving bodies, after scrutiny by the sections.
When the project is complete the sponsoring agency must send a completion report, the PC4. Seldom is this report completed and hence there is little evaluation of the work done and its proper costing. After 5 years of the completion of the project, an evaluation report, PC5, reports on the performance of the project comparing it to the stated expectations set out in the PC1. Once again, these reports are seldom if ever completed. Altogether, role of P&DD is to approve projects and maintaining expenditure management afterwards. 

Too Many Projects, Too Little Return
The technical details of policy and projects such as basis of evidence, cost-benefit,
rates of return and rigorous feasibility or sensitivity analysis have gradually been
withdrawn from senior policymaking forums.  Looking strictly at the project
development and management system, several weaknesses have crept into the system, lowering their impact and rate of return.

These are:

1) Projects are approved without due diligence. Feasibilities, cost-benefit analysis, spatial determination, and several other details are often subject to political or other considerations. Approvals are pushed through with executive fiat.

2) Projects frequently have large cost overruns. Using a selection of ADP projects overruns are frequent and quite large. This is a combination of poor project management, infrequent delays leading to cost escalation as well as poor initial preparation.

3) Excessive focus on brick and mortar. The bulk of the investment is in hard infrastructure such and link roads are the biggest components. Even in the social sectors and other sectors, departments are interested in brick and mortar and even the approval process favors that.

(To be continued by highlighting proposals for improvement)

Mr. Sajjad Hyder joined P&DD, as Research Officer (BS-17), in 1993 and worked in all the sectors of economy, undertaking research studies and region’s policy development initiatives for socioeconomic development. Main research studies include: Northern Areas Strategy for Sustainable Development, in collaboration with IUC Pakistan, Norther Ares Report on Participatory Poverty Assessment in collaboration with planning commission Pakistan, and Gilgit Baltistan Economic Report {Broadening the Transformation}, a joint venture with ADB and world bank. His contribution in major project interventions include Pakistan Social Action Program, under which significant impact was seen in primary education, primary health care and rural water supply and sanitation in this region.  Altogether, Mr. Sajjad Hyder, as young officer {that time}, had acted a leading role in SAP interventions as a catalyst.  

In the years ahead, Mr. Sajjad Hyder, was elevated to the positions of Assistant Chief (BS-18), Deputy Chief (BS -19), and Chief Economist (BS-20), having commendable contribution (s) in the socioeconomic development of Gilgit=Baltistan.

About Author

Continue Reading

Opinion

Challenges in Delivering Services in Gilgit-Baltistan

Avatar photo

Published

on

In November 2021, I joined the Soni Jawari Center for Public Policy (SJCPP) as a Junior Scholar. The SJCPP was newly established at the time, and its primary goal was to conduct policy-oriented research on how to improve the performance of public services in Gilgit-Baltistan. The SJCPP also aimed to develop partnerships with development agencies and advise the government of Gilgit-Baltistan on policy issues. As part of its work, the SJCPP began collecting data and consulting with stakeholders to identify the challenges that institutions face in delivering social protection services in Gilgit-Baltistan. The SJCPP’s first stakeholder consultation session was held on January 3, 2023, with government officials from both provincial and federal organizations. The second stakeholder consultation session was held with representatives from civil society, the private sector, and beneficiary organizations. These workshops were organized to develop a social protection policy for Gilgit-Baltistan. In this article, we will explore the challenges that institutions face in delivering services, with a specific focus on social protection services.

The launching ceremony of Gilgit-Baltistan Social Protection Policy.

Firstly, Social protection services in Gilgit-Baltistan are not available in all areas, especially in remote and hard-to-reach communities. This is due to the fragmented geography of GB, with many valleys located in far-flung areas that lack road access and network facilities. Service providers find it difficult and costly to reach these areas, so they often focus on providing services in urban areas. This problem could be addressed by developing infrastructure in remote areas, such as building roads and improving telecommunications. Service providers could also hire more staff to reach these areas.

Secondly, there is a lack of coordination between service providers in Gilgit-Baltistan, leading to overlapping services. This is because there is no central database of all regional beneficiaries. As a result, some beneficiaries receive services multiple times, while others do not receive any services at all. One solution to this problem is to create a central database of all beneficiaries in Gilgit-Baltistan. This would allow service providers to coordinate their efforts and ensure that no beneficiary is left behind. Moreover, there is a need to improve communication and collaboration between service providers. This could be done through regular meetings and workshops.

During the workshops, we learned that there is no clear definition of who is eligible to receive social protection services in Gilgit-Baltistan. This is a problem because it can lead to services being provided to people who do not need them, while those who are most in need may be excluded. Well-defined beneficiary identification criteria are essential to ensure that social protection services are targeted to those who need them most. These criteria should be based on objective factors, such as income, assets, and vulnerability. They should also be transparent and easy to understand so that people can be sure that they are eligible to receive services.

Further, for the beneficiary identification process, the provincial departments need to coordinate with LSO, community organizations, and village organizations because they are in a better position to identify poor people/households in their respective rural areas.

Another challenge that service providers face in Gilgit-Baltistan is the lack of internet connectivity in remote areas. This lack of connectivity creates a barrier to effective communication and service delivery. For example, service providers may not be able to access online databases or communicate with other service providers in real-time. This can lead to delays in service delivery and can make it difficult to target services to those who need them most. The government of Gilgit-Baltistan should work to improve internet connectivity in remote areas. This could be done by investing in infrastructure, such as building new towers and laying fiber optic cables. The government could also provide subsidies to internet service providers to make internet access more affordable.

In conclusion, there are a number of challenges that institutions face in delivering social protection services in Gilgit-Baltistan. These challenges include limited geographical coverage, overlapping of services, lack of beneficiary identification criteria, and lack of internet connectivity. These challenges can make it difficult to target social protection services to those who need them most. The government of Gilgit-Baltistan should work to address these challenges by developing infrastructure, improving coordination between service providers, and clarifying beneficiary identification criteria. The government should also work to improve internet connectivity in remote areas. By addressing these challenges, the government can help to ensure that social protection services are delivered effectively to those who need them most.

About Author

Continue Reading

Current Affairs

Unlocking Economic and Strategic Benefits: The Gwadar-Kashgar Railway Project

Avatar photo

Published

on

The Gwadar-Kashgar railway project is a significant infrastructure project that will connect the deep-water port of Gwadar in southwestern Pakistan to the city of Kashgar in China’s northwestern Xinjiang region. The project is part of China’s Belt and Road Initiative (BRI) and is expected to bring significant economic and strategic benefits to both Pakistan and China. In this article, we will explore the economic and strategic benefits of the project, as well as some of the environmental, security, financial, and geopolitical implications of the project.

Economic Benefits:

The Gwadar-Kashgar railway project is expected to transform the economies of both Pakistan and China. The project will provide a more efficient and cost-effective way of transporting goods between the two countries, opening up new trade routes and creating new job opportunities. The project will also have a transformative impact on the economy of Gilgit-Baltistan, providing new avenues for growth and development in the region. The railway line will connect China’s western region to Pakistan’s Gwadar port, giving China access to the Arabian Sea and a new trade route to the rest of the world. This will provide new markets and create new opportunities for economic growth and development.

Strategic Benefits:

The project will enhance Pakistan’s strategic importance as a key player in the region, with the potential to bring in significant investments and enhance its position as a regional power. It will also improve Pakistan’s energy security and reduce its dependence on existing trade routes that are vulnerable to geopolitical risks. The project will provide China with a new trade route to the Arabian Sea, diversify its energy supply, and enhance its strategic presence in the region. The project will also have broader strategic benefits for the wider region, helping to enhance regional stability and reduce the potential for conflict.

Security Concerns:

The Gwadar-Kashgar railway project, as a major infrastructure project, raises several security concerns. The project passes through some areas that are currently affected by security concerns, including Balochistan and Xinjiang. These areas have experienced various incidents of terrorism, separatism, and unrest in recent years, which could pose a security threat to the project.

The security of the project will be a key concern for both Pakistan and China. Pakistan has faced significant security challenges in the past, particularly in its Balochistan province, where separatist groups have been active. These groups have targeted various infrastructure projects, including the Gwadar port, which has faced security threats in the past. Therefore, ensuring the security of the Gwadar-Kashgar railway project will be a major challenge for Pakistan.

Similarly, Xinjiang, China’s westernmost province, has faced security challenges in recent years, particularly with regards to its Uyghur population. The Chinese government has been accused of human rights violations against the Uyghurs, and there have been reports of violent incidents in the region. The project’s route passes through Xinjiang, and there are concerns about the potential for security incidents in the region that could disrupt the project’s construction or operation.

Furthermore, the project could also have broader security implications for the region. The project’s proximity to Iran and Afghanistan, two countries with complex security situations, could pose additional security risks. The project could also be vulnerable to cyber-attacks, particularly given its reliance on digital technologies and infrastructure.

To mitigate security risks, both Pakistan and China will need to take steps to ensure the security of the project. This could involve deploying additional security personnel, implementing stricter security measures, and collaborating with local communities to address security concerns. The project’s planners will need to conduct a thorough risk assessment to identify potential security threats and develop appropriate mitigation strategies.

The security of the Gwadar-Kashgar railway project is a major concern, given the security challenges in the areas through which it passes. Pakistan and China will need to take proactive steps to ensure the security of the project and mitigate potential security risks. By doing so, they can help ensure the successful completion and operation of the project, and unlock its significant economic and strategic benefits.

Financing and Funding:

The cost of the project is estimated to be around $58 billion, making it one of the largest infrastructure projects in the world. The project’s funding and financing arrangements will be a key consideration, and it is likely that a combination of public and private financing will be used to fund the project.

Geopolitical Implications:

The Gwadar-Kashgar railway project has significant geopolitical implications for the region, particularly in terms of its impact on the balance of power in South Asia and Central Asia. The project will not only strengthen economic ties between China and Pakistan but also have wider implications for the region’s security and political landscape.

Firstly, the project could lead to a significant shift in the balance of power in South Asia. The railway will provide China with a direct link to the Arabian Sea, which will help it bypass the strategically vulnerable Malacca Strait and reduce its dependence on the South China Sea for maritime trade. This will enhance China’s economic and military presence in the Indian Ocean region, and could potentially pose a challenge to India’s traditional dominance in the region.

Secondly, the project will increase Pakistan’s strategic significance for China. Pakistan is already a key partner in China’s Belt and Road Initiative, and the completion of the Gwadar-Kashgar railway project will further strengthen their strategic partnership. This will enhance China’s ability to project its influence in the region, particularly in the context of the China-India rivalry.

Thirdly, the project will have significant implications for Central Asia. The railway will provide China with a direct link to the resource-rich Central Asian states, which are strategically located at the crossroads of Asia and Europe. This will enable China to expand its economic influence in the region and challenge Russia’s traditional dominance in Central Asia.

Fourthly, the project could potentially exacerbate existing tensions in the region. The project passes through areas that are affected by security concerns, including Balochistan and Xinjiang, and could potentially exacerbate ethnic and religious tensions in the region. Additionally, the project could potentially heighten tensions between India and Pakistan, particularly given India’s concerns about China’s growing influence in the region.

The Gwadar-Kashgar railway project has significant geopolitical implications for the region. While the project has the potential to strengthen economic ties between China and Pakistan and unlock significant economic and strategic benefits, it also poses potential security risks and could potentially exacerbate existing tensions in the region. The project’s planners will need to carefully consider these implications and develop appropriate mitigation strategies to ensure its success

Environmental Impact:

The Gwadar-Kashgar railway project has the potential to cause significant environmental damage, particularly to sensitive ecosystems in Gilgit-Baltistan. It is important for the project’s planners to take steps to minimize the environmental impact of the project.

Conclusion:

The Gwadar-Kashgar railway project is a major milestone in the economic and strategic partnership between Pakistan and China. The project has the potential to transform the economies of both countries, as well as the wider region. It will provide a new trade route to the rest of the world, opening up new markets and creating new opportunities for economic growth and development. The project will also have significant strategic benefits, enhancing the strategic importance of both Pakistan and China and reducing their dependence on existing trade routes that are vulnerable to geopolitical risks. However, it is important to consider the environmental, security, financial, and geopolitical implications of the project as well. By doing so, we can ensure that the project delivers on its promise of unlocking economic and strategic benefits for all stakeholders

About Author

Continue Reading

Trending